Construction Update 5.27.25
 
By Secretary CHRISTINE DENNETT
May 27, 2025
 

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination
• Excavation equipment was mobilized today, and soil removal is scheduled to begin on Wednesday, 5/28.
• Block work is underway and expected to be completed this week in preparation for the upcoming precast mezzanine installation.
• A crane and steel installation crew are scheduled to re-mobilize on Monday, 6/2 to begin installing the precast mezzanine deck, which is expected to take approximately two days.
• Following the mezzanine installation, steel erection activities will continue over the course of five working days, focusing on setting the remaining structural steel elements.
• Once the crane demobilizes, crews will continue to:
o Complete all steel connections
o Install remaining metal decking
o Verify alignment and level of all structural members

Steel Installation
Structural steel erection is progressing steadily. Current work is concentrated on the west side of the building, including:
• Bolted connections between beams and columns
• Installation of metal decking at the second floor and roof
• Straightening and leveling of steel framing components

Masonry Work (Updated!)
Block work continues this week in the southwest portion of the building, including the elevator, fill station, and shower area, to support the upcoming precast work.

MEPFP Coordination
Work continues on the mechanical, electrical, plumbing, and fire protection systems. Crews are roughing in piping, conduit, and electrical wiring throughout the newly enclosed areas. Trade coordination is ongoing to keep progress aligned with the construction schedule.

Access and Parking
• No construction-related parking is permitted on Elm Street or Memorial Drive.
• All deliveries must enter the site via King Street.
• Any necessary access via Memorial Drive will be coordinated and communicated in advance.

Environmental Safety Measures
Silt fences and silt baskets remain in place to manage erosion and sediment control. These systems are monitored regularly to ensure compliance with environmental standards.

Community Engagement
The Fire District encourages residents to stay informed through the District’s website and community bulletins. Project updates will continue to highlight major milestones, schedule adjustments, and any anticipated traffic impacts. Community feedback is always welcome.

Contact:
For more information, please reach out to the New Castle Fire District No. 1 Project Committee at:
📧 project@ncfd1.org