New Castle Fire District No.1

 
 

Upcoming Events

11/17/2025
Project Meeting with Contractors (weekly)

11/19/2025
Board of Commissioners Regular Meeting

11/24/2025
Project Meeting with Contractors (weekly)

12/01/2025
Project Meeting with Contractors (weekly)

12/08/2025
Project Meeting with Contractors (weekly)

12/08/2025
Board of Commissioners Project Special Meeting

12/09/2025
Annual Fire District Election

12/15/2025
Project Meeting with Contractors (weekly)

12/17/2025
Board of Commissioners Regular Meeting

12/22/2025
Project Meeting with Contractors (weekly)

12/29/2025
Project Meeting with Contractors (weekly)

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
377,743
Visitors Today
Nov 11, 2025
115
Construction Update 8.5.25
Email Print RSS Facebook Twitter RSS

By Secretary CHRISTINE DENNETT
August 5, 2025

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Sewer Permit Approved: The Town of New Castle approved the sewer permit earlier today for both the sewer repair points and the sewer connection work. The signed permit has been received, and scheduling is now underway for the site contractor to mobilize and perform the necessary work.

Construction Progress: Structural steel framing and metal decking work are ongoing. Concrete planters were poured yesterday, and crews are preparing for the second-floor deck concrete pour and additional concrete work at grade level. Exterior brick and precast materials will be delivered following approval of the masonry mockup.

Interior Work: Layout and installation of sheetrock wall framing on the second floor is underway. Steel plates are being installed on the mezzanine exterior to support the topping slab pour and allow framing to continue.
A pressure test of the sewer piping for the apparatus bay trench drains is scheduled, followed by backfilling operations.

Framing and Labor Coordination: The general contractor has requested additional carpenters this week and next week to maintain momentum on second-floor framing activities.

Efforts are ongoing to increase masonry labor on site in order to expedite the completion of blockwork. This work is critical to setting roof trusses and enclosing the building. Resource constraints have been noted due to peak-season workload across multiple projects, as the blockwork scope was delayed into summer months.

Site Work and Coordination

Outstanding work includes:
• Backfilling the sewer line in the apparatus bay
• Repairing the storm line at the north side of the site
• Coordinating underground piping and structure installation at the north end after masonry and drainage work are complete

Masonry and MEP Progress: Masonry work continues in the elevator lobby, southwest quadrant, and along the west perimeter of the mezzanine. Mechanical, electrical, plumbing, and fire protection rough-ins are progressing behind masonry walls in coordination with blockwork.

Access and Parking
• No construction-related parking is permitted on Elm Street or Memorial Drive.
• All deliveries must enter from King Street.
• Access via Memorial Drive will be scheduled and communicated in advance.

Environmental Safety Measures: Silt fences and silt baskets remain in place and are regularly inspected for compliance with environmental protection standards.

Community Engagement

The District remains committed to keeping the community informed:
• Visit the District’s website or check community bulletins for the latest updates.
• Project reports will continue to outline key milestones, traffic impacts, and schedule adjustments.

💬 Community feedback is encouraged and welcome.

📧 For more information, please reach out to the New Castle Fire District No. 1 Project Committee at: project@ncfd1.org

Attachments:
Attachment New Castle FDPT00000000.mov  (132,990k)
 

Add a Comment Add a Comment 0 Comment(s)


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)