Construction Update 9.15.25

 
By Secretary CHRISTINE DENNETT
September 15, 2025
 

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Construction Progress
• Phase One substantial completion remains targeted for March 2026.
• All roof trusses have been successfully installed, and the crane has demobilized ahead of schedule—a significant milestone in the structural work.
• Carpenters are now shifting focus to installing roof sheathing and framing on the west side of the building to prepare for upcoming brickwork.
• Subbase and gravel work is progressing in both the East rooms and the apparatus bay in preparation for interior slab work.
• Once this is complete, trench drain excavation will begin in the apparatus bay and bathroom/shower areas.
• After trench excavation, the concrete base for the trench drains will be poured. This will be followed by:
o Placement of rebar for the slab on grade
o Installation of radiant heating tubing
o Setting of plumbing floor drains
• The slab pour remains scheduled for early October.

Framing and Labor Coordination
• Additional carpenters have been requested to maintain progress on second-floor framing.
• Efforts to increase masonry labor continue, as completion of blockwork is critical to progressing with the building enclosure.
• Labor resources remain in high demand due to regional peak-season activity.

Access and Parking
• No construction-related parking is permitted on Elm Street or Memorial Drive.
• All deliveries must enter from King Street.
• Access via Memorial Drive will be scheduled and communicated in advance.

Environmental Safety Measures: Silt fences and silt baskets remain in place and are regularly inspected for compliance with environmental protection standards.

Community Engagement

The District remains committed to keeping the community informed:
• Visit the District’s website or check community bulletins for the latest updates.
• Project reports will continue to outline key milestones, traffic impacts, and schedule adjustments.

💬 Community feedback is encouraged and welcome.

📧 For more information, please reach out to the New Castle Fire District No. 1 Project Committee at: project@ncfd1.org