New Castle Fire District No.1

 
 

Upcoming Events

06/30/2025
Project Meeting with Contractors (weekly)

07/07/2025
Project Meeting with Contractors (weekly)

07/14/2025
Project Meeting with Contractors (weekly)

07/14/2025
Board of Commissioners Project Special Meeting

07/16/2025
Board of Commissioners Regular Meeting

07/21/2025
Project Meeting with Contractors (weekly)

07/28/2025
Project Meeting with Contractors (weekly)

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
319,553
Visitors Today
Jun 30, 2025
476
Construction Update 6.24.25
Email Print RSS Facebook Twitter RSS

By Secretary CHRISTINE DENNETT
June 24, 2025

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination

• The mobile crane returned to the site on Thursday, June 19, and has been actively supporting the erection of structural steel.
• Crews are continuing to complete bolted connections between steel beams and columns installed last week.
• By the end of next week, work is expected to shift to the placement of metal decking along the second floor and roof.
• Masonry crews will remobilize on-site Thursday, June 26, to resume block work in the southwest portion of the building, including the elevator lobby, corridor, unisex toilets, and standby room. They are expected to remain on-site through the end of August to complete block installation throughout the building.
• MEPFP trades (mechanical, electrical, plumbing, and fire protection) have been notified to coordinate with masonry crews and will begin installing pipe, conduit, and devices behind the block walls starting Thursday, June 26.

Steel Installation

Structural steel erection is progressing steadily with current activity focused on:

• Completing bolted beam-to-column connections
• Straightening and leveling of framing members
• Upcoming: Metal deck installation on the second floor and roof anticipated by end of next week

Masonry Work

Block work continues to support the upcoming precast installation:

• Currently focused in the southwest portion (elevator, fill station, shower area, unisex toilets, hydration room, standby room)
• Crews will expand block installation across the remainder of the building through August

Site Work

• Stormwater detention system installation is expected to be complete by June 25.
• Following this, excavation is planned for the southwest planters, where form and concrete work will begin shortly after.
• Materials on the east side of the site will be relocated to the west side, clearing space for site crews to initiate sewer connection work.
• Site preparation continues along the future driveway to Memorial Drive, with sand filter F-3-A installation scheduled and underground detention system F-2 prepared for delivery and inspection.

Crane Operations

The mobile crane remains on-site, assisting in:

• Precast mezzanine setting
• Steel erection

⚠️ Safety Reminder: No other trades are permitted within the crane swing radius during operations.

MEPFP Coordination

• Trades are roughing in piping, conduits, and electrical systems throughout enclosed areas.
• Crews are now sequencing their work to proceed behind masonry block installation for efficient progress.

Access and Parking

• No construction-related parking is permitted on Elm Street or Memorial Drive
• All deliveries must enter from King Street
• Access via Memorial Drive will be scheduled and communicated in advance

Environmental Safety Measures

• Silt fences and silt baskets remain in place and are regularly inspected for compliance with environmental protection standards

Community Engagement

The District remains committed to keeping the community informed:

• Visit the District’s website or check community bulletins for the latest updates
• Project reports will continue to outline key milestones, traffic impacts, and schedule adjustments

💬 Community feedback is encouraged and welcome

Contact 📧 For more information, please reach out to the New Castle Fire District No. 1 Project Committee at: project@ncfd1.org


Add a Comment Add a Comment 0 Comment(s)


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)