Work continues on the NCFD 1 Chappaqua Firehouse Extension despite cold, snowy conditions. A total of 32 workers and visitors were on site this week. Town of New Castle and Tectonic Engineering inspections were completed and approved for storm piping, soil compaction, and initial kitchen gas piping / hood installation. Major progress included drywall installation and taping, HVAC ductwork and piping, electrical rough-in, site backfilling and HDPE storm piping.