New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY Key Updates
Progress and Coordination • Crews continue working on structural steel erection. • Metal decking and stud installation are underway. o A third-party engineering firm will be onsite to inspect the stud work. • Safety cabling installation has begun preparing for the second-floor concrete pour. • Concrete crews are scheduled to return on Friday, July 11, to begin work on the second-floor deck. • In addition to the deck work, concrete activities will include: o Pouring the southwest planters o Placing the retaining wall along the driveway to Memorial Drive o Pouring the 2” topping slab on the mezzanine • Turnover of the second-floor deck is scheduled for Monday, July 8, in preparation for concrete work.
Excavation Activities Excavation crews are scheduled to remobilize on Tuesday, July 8. Planned tasks include: • Retaining Wall ‘B’ Excavation: expected to take 0.5–1 day. • Planter Wall #2: Finish excavation; potential gas line conflict remains under review. • Under-Slab Trenching: o For three trench drains o For the water fill line • Backfill and Compaction: Two remaining pits at the northwest area, pending readiness for structural fill. • Rigid Insulation (2" XPS, R-10) • Existing Sanitary Sewer Line Repairs • Oil-Water Separator: Installation to begin upon delivery of precast unit to site. • Drainage Structures: Awaiting precast structure delivery from supplier; coordination ongoing. • Precast Sand Filter TD C-2-1: Scheduled for delivery; installation pending clearance of adjacent masonry activities. • Water Quality Structures (3 total): These are long-lead items (4–6 weeks).
Masonry & Framing • Masonry crews are actively working in the southwest quadrant of the building. • Masonry work resumed on June 26 in the elevator lobby, corridor, unisex toilets, and standby room. This work will continue throughout the building into August. • Elevator shaft construction continues to progress. • Exterior block work has begun at the west perimeter of the mezzanine. • Mechanical sleeves for piping systems were delivered and are being integrated with masonry installations.
MEPFP Coordination • Mechanical, electrical, plumbing, and fire protection trades are working on rough-ins behind masonry walls. • Work is carefully sequenced to follow the pace of masonry block installation to ensure efficient progress.
Site Work • Excavation for the southwest planters is complete and formwork has begun, leading into upcoming concrete placement. • Materials are being moved from the east to the west side of the site to clear space for sewer connection activities. • Work is ongoing at the future driveway to Memorial Drive, including: o Installation of sand filter F-3-A o Preparation and inspection for the underground detention system F-2
Access and Parking • No construction-related parking is permitted on Elm Street or Memorial Drive. • All deliveries must enter from King Street. • Access via Memorial Drive will be scheduled and communicated in advance.
Environmental Safety Measures • Silt fences and silt baskets remain in place and are regularly inspected for compliance with environmental protection standards.
Community Engagement The District remains committed to keeping the community informed: • Visit the District’s website or check community bulletins for the latest updates. • Project reports will continue to outline key milestones, traffic impacts, and schedule adjustments. 💬 Community feedback is encouraged and welcome.
📧 For more information, please reach out to the New Castle Fire District No. 1 Project Committee at: project@ncfd1.org |