New Castle Fire District No.1

 
 

Upcoming Events

07/16/2025
Board of Commissioners Regular Meeting

07/21/2025
Project Meeting with Contractors (weekly)

07/28/2025
Project Meeting with Contractors (weekly)

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
327,669
Visitors Today
Jul 16, 2025
209
Construction Update 7.8.25
Email Print RSS Facebook Twitter RSS

By Secretary CHRISTINE DENNETT
July 8, 2025

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY
Key Updates

Progress and Coordination
• Crews continue working on structural steel erection.
• Metal decking and stud installation are underway.
o A third-party engineering firm will be onsite to inspect the stud work.
• Safety cabling installation has begun preparing for the second-floor concrete pour.
• Concrete crews are scheduled to return on Friday, July 11, to begin work on the second-floor deck.
• In addition to the deck work, concrete activities will include:
o Pouring the southwest planters
o Placing the retaining wall along the driveway to Memorial Drive
o Pouring the 2” topping slab on the mezzanine
• Turnover of the second-floor deck is scheduled for Monday, July 8, in preparation for concrete work.

Excavation Activities
Excavation crews are scheduled to remobilize on Tuesday, July 8. Planned tasks include:
• Retaining Wall ‘B’ Excavation: expected to take 0.5–1 day.
• Planter Wall #2: Finish excavation; potential gas line conflict remains under review.
• Under-Slab Trenching:
o For three trench drains
o For the water fill line
• Backfill and Compaction: Two remaining pits at the northwest area, pending readiness for structural fill.
• Rigid Insulation (2" XPS, R-10)
• Existing Sanitary Sewer Line Repairs
• Oil-Water Separator: Installation to begin upon delivery of precast unit to site.
• Drainage Structures: Awaiting precast structure delivery from supplier; coordination ongoing.
• Precast Sand Filter TD C-2-1: Scheduled for delivery; installation pending clearance of adjacent masonry activities.
• Water Quality Structures (3 total): These are long-lead items (4–6 weeks).

Masonry & Framing
• Masonry crews are actively working in the southwest quadrant of the building.
• Masonry work resumed on June 26 in the elevator lobby, corridor, unisex toilets, and standby room. This work will continue throughout the building into August.
• Elevator shaft construction continues to progress.
• Exterior block work has begun at the west perimeter of the mezzanine.
• Mechanical sleeves for piping systems were delivered and are being integrated with masonry installations.

MEPFP Coordination
• Mechanical, electrical, plumbing, and fire protection trades are working on rough-ins behind masonry walls.
• Work is carefully sequenced to follow the pace of masonry block installation to ensure efficient progress.

Site Work
• Excavation for the southwest planters is complete and formwork has begun, leading into upcoming concrete placement.
• Materials are being moved from the east to the west side of the site to clear space for sewer connection activities.
• Work is ongoing at the future driveway to Memorial Drive, including:
o Installation of sand filter F-3-A
o Preparation and inspection for the underground detention system F-2

Access and Parking
• No construction-related parking is permitted on Elm Street or Memorial Drive.
• All deliveries must enter from King Street.
• Access via Memorial Drive will be scheduled and communicated in advance.

Environmental Safety Measures
• Silt fences and silt baskets remain in place and are regularly inspected for compliance with environmental protection standards.

Community Engagement
The District remains committed to keeping the community informed:
• Visit the District’s website or check community bulletins for the latest updates.
• Project reports will continue to outline key milestones, traffic impacts, and schedule adjustments.
💬 Community feedback is encouraged and welcome.

📧 For more information, please reach out to the New Castle Fire District No. 1 Project Committee at: project@ncfd1.org


Add a Comment Add a Comment 0 Comment(s)


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)