New Castle Fire District No.1

 
 

Upcoming Events

07/07/2025
Project Meeting with Contractors (weekly)

07/14/2025
Project Meeting with Contractors (weekly)

07/14/2025
Board of Commissioners Project Special Meeting

07/16/2025
Board of Commissioners Regular Meeting

07/21/2025
Project Meeting with Contractors (weekly)

07/28/2025
Project Meeting with Contractors (weekly)

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
321,276
Visitors Today
Jul 04, 2025
87
Construction Update 7.2.25
Email Print RSS Facebook Twitter RSS

By Secretary CHRISTINE DENNETT
July 2, 2025

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination

• Crews continue working on structural steel erection, including bolted beam-to-column connections and alignment of framing members.
• Metal decking and stud installation are underway.
o A third-party engineering firm will be onsite to inspect the stud work.
• Safety cabling installation is scheduled to begin next week following completion of decking activities, preparing for the second-floor concrete pour.
• Concrete crews are scheduled to return on Wednesday, July 9, to:
o Continue work on the southwest planters
o Pour concrete on the second-floor deck
• Masonry work resumed on June 26 in the southwest section of the building (elevator lobby, corridor, unisex toilets, standby room).

Work will expand throughout the building and continue through August.

Masonry & Framing

• Masonry crews are actively working in the southwest quadrant of the building.
• Elevator shaft construction continues to progress.
• Exterior block work has begun at the west perimeter of the mezzanine.
• Mechanical sleeves for piping systems were delivered and are being integrated with masonry installations.

MEPFP Coordination

• Mechanical, electrical, plumbing, and fire protection trades are working on rough-ins behind masonry walls.
• Work is carefully sequenced to follow the pace of masonry block installation to ensure efficient progress.

Site Work
• The stormwater detention system is scheduled for completion by June 25.
• Excavation for the southwest planters will follow immediately and lead into formwork and concrete placement.
• Materials are being moved from the east to the west side of the site to clear space for sewer connection activities.
• Work is ongoing at the future driveway to Memorial Drive, including:
o Installation of sand filter F-3-A
o Preparation and inspection for the underground detention system F-2

Access and Parking

• No construction-related parking is permitted on Elm Street or Memorial Drive
• All deliveries must enter from King Street
• Access via Memorial Drive will be scheduled and communicated in advance

Environmental Safety Measures

• Silt fences and silt baskets remain in place and are regularly inspected for compliance with environmental protection standards

Community Engagement

The District remains committed to keeping the community informed:
• Visit the District’s website or check community bulletins for the latest updates
• Project reports will continue to outline key milestones, traffic impacts, and schedule adjustments

💬 Community feedback is encouraged and welcome

Contact 📧 For more information, please reach out to the New Castle Fire District No. 1 Project Committee at: project@ncfd1.org

🎆 As we celebrate Independence Day and the 249th birthday of the United States, the New Castle Fire District No. 1 wishes everyone a joyful, safe, and fire-smart holiday. Please be mindful of fire safety, especially when using grills, fireworks, or open flames. Let's all do our part to protect our community.


Add a Comment Add a Comment 0 Comment(s)


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)