New Castle Fire District No.1

 
 

Upcoming Events

06/30/2025
Project Meeting with Contractors (weekly)

07/07/2025
Project Meeting with Contractors (weekly)

07/14/2025
Project Meeting with Contractors (weekly)

07/14/2025
Board of Commissioners Project Special Meeting

07/16/2025
Board of Commissioners Regular Meeting

07/21/2025
Project Meeting with Contractors (weekly)

07/28/2025
Project Meeting with Contractors (weekly)

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
319,485
Visitors Today
Jun 30, 2025
408

Welcome to New Castle Fire District No.1


he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.

Divider
No Caption Construction Update 6.24.25

Secretary CHRISTINE DENNETT, June 24

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination

• The mobile crane returned to the site on Thursday, June 19, and has been actively supporting the erection of structural steel.
• Crews are continuing to complete bolted connections between steel beams and columns installed last week.
• By the end of next week, work is expected to shift ... (Full Story & Photos)

Divider
Construction Update 6.17.25

Secretary CHRISTINE DENNETT, June 17

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination

• The crane is returning to the site today and will remain on-site throughout the week to resume structural steel erection.
• Excavation equipment has been mobilized and soil removal is underway.
• Block work is ongoing to support the precast mezzanine installation.
• Once the crane demobilizes, ... (Full Story)


Divider
Construction Update 6.4.25

Secretary CHRISTINE DENNETT, June 04

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination
• Excavation equipment has been mobilized and soil removal is underway.
• Block work is in progress in preparation for the precast mezzanine installation.
• A crane and steel installation crew will begin installing the precast mezzanine deck, which is expected to take approximately two ... (Full Story)


Divider
Construction Update 5.27.25

Secretary CHRISTINE DENNETT, May 27

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination
• Excavation equipment was mobilized today, and soil removal is scheduled to begin on Wednesday, 5/28.
• Block work is underway and expected to be completed this week in preparation for the upcoming precast mezzanine installation.
• A crane and steel installation crew are scheduled to ... (Full Story)


Divider
Construction Update 5.19.25

Secretary CHRISTINE DENNETT, May 19

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination

Masonry Work (Updated!)
Block work will continue throughout the week, with masonry teams fully mobilized on site. The mason has started work on the southwest portion of the project, near the elevator, fill station, and shower area.

Mechanical, Electrical, Plumbing, and Fire Protection ... (Full Story)


Divider
Construction Update 5.14.25

Secretary CHRISTINE DENNETT, May 14

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination

Steel Installation (Updated!)
Steel erection is progressing steadily, officially taking the project vertical. This week, crews are focusing efforts on the west side of the project, working on completing bolted connections between steel beams and columns, installing metal decking on the ... (Full Story & Photos)

No Caption
Divider
Construction Update 5.7.25

Secretary CHRISTINE DENNETT, May 07

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates:

Progress and Coordination:
• Steel Installation (Updated!):
Steel erection is underway, officially taking the project vertical. Work includes fall fittings, completing bolted connections between steel beams and columns, installing metal decking, and ensuring all beams are level.
• Masonry Work (New!):
The mason ... (Full Story)


Divider
Construction Update 4.30.25

Secretary CHRISTINE DENNETT, April 30

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates:

Progress and Coordination:

•Crane & Steel Installation (New!):

Exciting milestone — the crane has been delivered, and the first steel has been installed, officially taking the project vertical! Steel erection, including fall protection fittings, will continue on the west side of the site.

•Masonry Work (New!):

Masonry ... (Full Story & Photos)

No Caption
Divider

Your feedback is important to us!  Feel free to sign the guestbook.


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)