New Castle Fire District No.1

 
 

Upcoming Events

There are currently no events
View All Events


Web Counters
Website Visitors
Since
March 15, 2023
418,851
Visitors Today
Feb 15, 2026
386

Welcome to New Castle Fire District No.1


he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.

Divider
Moody's confirms Aa1 bond ratings

NCFD1 District Secretary, February 13

New York, February 13, 2026 -- Moody's Ratings (Moody's) has confirmed New Castle Fire District No.1, NY's Aa1 issuer and general obligation limited tax (GOLT) bond ratings. This action concludes a review for possible downgrade that was initiated on December 9th, 2025, in conjunction with the release of the US Special Purpose Districts methodology. The district has approximately $16.9 million in general ... (Full Story)


Divider
Construction Update - 02.12.2026

NCFD1 District Secretary, February 12

The sand filter structure adjacent to the building was delivered and partially installed today. Installation will be completed tomorrow, with the Town scheduled to inspect the installation tomorrow afternoon. Key Construction measured and taped out the openings to be made in the existing firehouse wall today, for coordinating with the asbestos abatement contractor. Other work is progressing. The ... (Full Story & Photos)

No Caption
Divider
PUBLIC NOTICE - SENTER STREET FIREHOUSE

NCFD1 District Secretary, February 08

A meeting of the Board of Fire Commissioners will be held on Wednesday February 11, 2026. Please click on the attached Public Notice for details.... (Full Story)


Divider
Construction Update - 01.30.26

NCFD1 District Secretary, January 30

Work continues on the NCFD 1 Chappaqua Firehouse Extension despite cold, snowy conditions. A total of 32 workers and visitors were on site this week. Town of New Castle and Tectonic Engineering inspections were completed and approved for storm piping, soil compaction, and initial kitchen gas piping / hood installation. Major progress included drywall installation and taping, HVAC ductwork and piping, ... (Full Story & Photos)

No Caption
Divider
Construction Update 01.14.26

Member NCFD1 Secretary, January 15

Project Overview
The modernization project continues to progress as crews work both inside and outside the building. This week, the carpenters are installing windows in the vestibule area and are continuing to install sheetrock on the 2nd floor.  The mechanical contractor is firestopping hydronic piping and continuing to install ductwork in the 2nd floor.  The plumbing contractor is working on pipe ... (Full Story)


Divider
Notice of Organizational Meeting

NCFD1 Secretary, January 09

The Organizational Meeting of New Castle Fire District No. 1 will commence at 6:30 p.m. on Wednesday, January 14, 2026, at 491 King Street, Chappaqua, New York.... (Full Story)


Divider
No Caption Construction Update 12.17.25

Secretary CHRISTINE DENNETT, December 17

New Castle Fire District No. 1
Modernization Project Update
Chappaqua, NY
December 17, 2025

Project Overview
The modernization project continues to progress as crews work both inside and outside the building as colder weather approaches. Phase One remains scheduled for substantial completion in April 2026. Additional schedule and sequencing information will be shared as it becomes available.

Exterior ... (Full Story & Photos)

Divider
Construction Update 12.3.25

Secretary CHRISTINE DENNETT, December 03

New Castle Fire District No. 1
Modernization Project Update
Chappaqua, NY

December 3, 2025

Project Overview
The modernization project continues to progress as crews work both inside and outside the building headed into colder weather. Phase One remains scheduled for substantial completion in April 2026.

Exterior & Structural Work
Brick and precast installation continues, with the north side expected ... (Full Story & Photos)

Site facing North
Site facing North

Divider

Your feedback is important to us!  Feel free to sign the guestbook.


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2026 Firehouse Solutions (A Service of Technology Reflections, Inc.)