|
Welcome to New Castle Fire District No.1
.jpg)

he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.
|
Construction Update 11.9.25
Secretary CHRISTINE DENNETT, November 09
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates – November 9, 2025
Overall Progress Phase One of the modernization project remains on schedule for substantial completion by March 2026. Crews are taking advantage of the mild fall weather to continue exterior and interior work before winter conditions arrive.
Exterior Work Brick and precast installation continues ... (Full Story & Photos)
|
Decorative Stonework Installation
|
|
|
Construction Update 10.27.25
Secretary CHRISTINE DENNETT, October 27
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates – October 27, 2025
Construction Progress
Phase One of the project remains on track for substantial completion by March 2026. Coordination between trades continues to ensure all systems and pours are scheduled efficiently ahead of colder weather.
Plumbing & Mechanical
The backflow preventers for the project have ... (Full Story & Photos)
|
Construction Update 10.13.25
Secretary CHRISTINE DENNETT, October 13
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates – October 13, 2025
Construction Progress Phase One of the project remains on track for substantial completion by March 2026.
Roof Work Shingle installation is complete. All lower roofs now have roofing material installed. Work on the upper roof, adjacent to the existing firehouse, will continue this week. Roof ... (Full Story & Photos)
|
Apparatus Bays
|
|
Construction Update 10.6.25 Sewer Lining Project
Secretary CHRISTINE DENNETT, October 06
As part of ongoing maintenance efforts, a sewer lining project is scheduled to take place on Wednesday, October 8th. The work is expected to be completed in one day.
Key Details: • Date of Work: Wednesday, October 8th • Duration: One day (weather permitting) • Traffic Impacts: There may be temporary traffic disruptions in the area while work is underway.
We are working diligently to minimize any ... (Full Story)
|
Construction Update 9.30.25
Secretary CHRISTINE DENNETT, September 30
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates – September 30, 2025
Construction Progress Phase One of the project remains on track for substantial completion by March 2026.
Roof Work The roofing crew has mobilized on-site and is progressing quickly. All shingle underlayment has been installed over the main roof truss system. Shingle installation is underway, ... (Full Story & Photos)
|
|
|
Construction Update 9.15.25
Secretary CHRISTINE DENNETT, September 15
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates
Construction Progress • Phase One substantial completion remains targeted for March 2026. • All roof trusses have been successfully installed, and the crane has demobilized ahead of schedule—a significant milestone in the structural work. • Carpenters are now shifting focus to installing roof sheathing and framing ... (Full Story & Photos)
|
|
Construction Update 8.25.25
Secretary CHRISTINE DENNETT, August 25
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates
Construction Progress • Phase One substantial completion March 2026. • Structural steel framing and metal decking work are ongoing. • Preparations continue for the second-floor deck concrete pour and additional at-grade concrete work. • Installation of the steel landing deck in the S04 stair enclosure is also underway.
Interior ... (Full Story & Photos)
|
West Side
|
Construction Update 8.13.25
Secretary CHRISTINE DENNETT, August 13
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates
Sewer Permit Approved
The Town of New Castle has approved the sewer permit for both the sewer repair points and connection work. The signed permit has been received, and scheduling is underway for the site contractor to mobilize and perform the necessary work.
Updated Schedule
Phase 1 of the firehouse is now ... (Full Story)
|
Your feedback is important to us! Feel free to sign the guestbook.
|