|
Welcome to New Castle Fire District No.1
.jpg)

he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.
|
Moody's confirms Aa1 bond ratings
NCFD1 District Secretary, February 13
New York, February 13, 2026 -- Moody's Ratings (Moody's) has confirmed New Castle Fire District No.1, NY's Aa1 issuer and general obligation limited tax (GOLT) bond ratings. This action concludes a review for possible downgrade that was initiated on December 9th, 2025, in conjunction with the release of the US Special Purpose Districts methodology. The district has approximately $16.9 million in general ... (Full Story)
|
Construction Update - 02.12.2026
NCFD1 District Secretary, February 12
The sand filter structure adjacent to the building was delivered and partially installed today. Installation will be completed tomorrow, with the Town scheduled to inspect the installation tomorrow afternoon. Key Construction measured and taped out the openings to be made in the existing firehouse wall today, for coordinating with the asbestos abatement contractor. Other work is progressing. The ... (Full Story & Photos)
|
|
Construction Update - 01.30.26
NCFD1 District Secretary, January 30
Work continues on the NCFD 1 Chappaqua Firehouse Extension despite cold, snowy conditions. A total of 32 workers and visitors were on site this week. Town of New Castle and Tectonic Engineering inspections were completed and approved for storm piping, soil compaction, and initial kitchen gas piping / hood installation. Major progress included drywall installation and taping, HVAC ductwork and piping, ... (Full Story & Photos)
|
|
Construction Update 01.14.26
Member NCFD1 Secretary, January 15
Project Overview The modernization project continues to progress as crews work both inside and outside the building. This week, the carpenters are installing windows in the vestibule area and are continuing to install sheetrock on the 2nd floor. The mechanical contractor is firestopping hydronic piping and continuing to install ductwork in the 2nd floor. The plumbing contractor is working on pipe ... (Full Story)
|
Notice of Organizational Meeting
NCFD1 Secretary, January 09
The Organizational Meeting of New Castle Fire District No. 1 will commence at 6:30 p.m. on Wednesday, January 14, 2026, at 491 King Street, Chappaqua, New York.... (Full Story)
|
|
Construction Update 12.17.25
Secretary CHRISTINE DENNETT, December 17
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY December 17, 2025
Project Overview The modernization project continues to progress as crews work both inside and outside the building as colder weather approaches. Phase One remains scheduled for substantial completion in April 2026. Additional schedule and sequencing information will be shared as it becomes available.
Exterior ... (Full Story & Photos)
|
|
Construction Update 12.3.25
Secretary CHRISTINE DENNETT, December 03
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
December 3, 2025
Project Overview The modernization project continues to progress as crews work both inside and outside the building headed into colder weather. Phase One remains scheduled for substantial completion in April 2026.
Exterior & Structural Work Brick and precast installation continues, with the north side expected ... (Full Story & Photos)
|
Site facing North
|
Your feedback is important to us! Feel free to sign the guestbook.
|