New Castle Fire District No.1

 
 

Upcoming Events

There are currently no events
View All Events


Web Counters
Website Visitors
Since
March 15, 2023
408,747
Visitors Today
Jan 21, 2026
168

Welcome to New Castle Fire District No.1


he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.

Divider
Construction Update 01.14.26

Member NCFD1 Secretary, January 15

Project Overview
The modernization project continues to progress as crews work both inside and outside the building. This week, the carpenters are installing windows in the vestibule area and are continuing to install sheetrock on the 2nd floor.  The mechanical contractor is firestopping hydronic piping and continuing to install ductwork in the 2nd floor.  The plumbing contractor is working on pipe ... (Full Story)


Divider
Notice of Organizational Meeting

NCFD1 Secretary, January 09

The Organizational Meeting of New Castle Fire District No. 1 will commence at 6:30 p.m. on Wednesday, January 14, 2026, at 491 King Street, Chappaqua, New York.... (Full Story)


Divider
No Caption Construction Update 12.17.25

Secretary CHRISTINE DENNETT, December 17

New Castle Fire District No. 1
Modernization Project Update
Chappaqua, NY
December 17, 2025

Project Overview
The modernization project continues to progress as crews work both inside and outside the building as colder weather approaches. Phase One remains scheduled for substantial completion in April 2026. Additional schedule and sequencing information will be shared as it becomes available.

Exterior ... (Full Story & Photos)

Divider
Construction Update 12.3.25

Secretary CHRISTINE DENNETT, December 03

New Castle Fire District No. 1
Modernization Project Update
Chappaqua, NY

December 3, 2025

Project Overview
The modernization project continues to progress as crews work both inside and outside the building headed into colder weather. Phase One remains scheduled for substantial completion in April 2026.

Exterior & Structural Work
Brick and precast installation continues, with the north side expected ... (Full Story & Photos)

Site facing North
Site facing North

Divider
No Caption Construction Update 11.17.25

Secretary CHRISTINE DENNETT, November 17

New Castle Fire District No. 1
Modernization Project Update
Chappaqua, NY

November 15, 2025

Project Overview

The modernization project continues to move forward, and Phase One will be substantially complete in April 2026. Crews are working inside and outside the building as we head into colder weather.

Exterior & Structural Work

Brick and precast installation is ongoing and will continue over ... (Full Story & Photos)

Divider
Construction Update 11.9.25

Secretary CHRISTINE DENNETT, November 09

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates – November 9, 2025

Overall Progress
Phase One of the modernization project remains on schedule for substantial completion by March 2026. Crews are taking advantage of the mild fall weather to continue exterior and interior work before winter conditions arrive.

Exterior Work
Brick and precast installation continues ... (Full Story & Photos)

Decorative Stonework Installation
Decorative Stonework Installation

Divider
No Caption Construction Update 10.27.25

Secretary CHRISTINE DENNETT, October 27

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates – October 27, 2025

Construction Progress

Phase One of the project remains on track for substantial completion by March 2026. Coordination between trades continues to ensure all systems and pours are scheduled efficiently ahead of colder weather.

Plumbing & Mechanical

The backflow preventers for the project have ... (Full Story & Photos)

Divider
Construction Update 10.13.25

Secretary CHRISTINE DENNETT, October 13

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates – October 13, 2025

Construction Progress
Phase One of the project remains on track for substantial completion by March 2026.

Roof Work
Shingle installation is complete. All lower roofs now have roofing material installed. Work on the upper roof, adjacent to the existing firehouse, will continue this week. Roof ... (Full Story & Photos)

Apparatus Bays
Apparatus Bays

Divider

Your feedback is important to us!  Feel free to sign the guestbook.


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2026 Firehouse Solutions (A Service of Technology Reflections, Inc.)