New Castle Fire District No.1

 
 

Upcoming Events

There are currently no events
View All Events


Web Counters
Website Visitors
Since
March 15, 2023
244,785
Visitors Today
Jan 26, 2025
44

Welcome to New Castle Fire District No.1


he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.

Divider
Construction Update 1.22.25

Secretary CHRISTINE DENNETT, January 22

New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, Concrete Pouring Underway
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make substantial progress, with essential construction activities advancing as planned.

Key Updates Include:

•Excavation Work: Excavation has been completed along the southwest section of the site, and work ... (Full Story)


Divider
Construction Update 1.15.25

Secretary CHRISTINE DENNETT, January 15

New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, Concrete Pouring Underway

Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make substantial progress, with essential construction activities advancing as planned.

Key Updates Include:

•Excavation Work: Excavation has been completed along the southwest section of the site, and work ... (Full Story)


Divider
Construction Update 1.8.25

Secretary CHRISTINE DENNETT, January 08

New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make significant strides, with key construction activities progressing on schedule.

Key Updates Include:

•Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing ... (Full Story)


Divider
Construction Update 12.31.24

Secretary CHRISTINE DENNETT, December 31

New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make significant strides with key construction activities progressing on schedule.

Key Updates Include:

•Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing ... (Full Story)


Divider
Construction Update 12.19.24

Secretary CHRISTINE DENNETT, December 19

New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make significant strides with key construction activities progressing on schedule.

Key Updates Include:
•Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing ... (Full Story & Photos)

No Caption
Divider
No Caption Construction Update 12.10.24

Secretary CHRISTINE DENNETT, December 10

New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project is progressing with key activities moving forward.

Key Updates Include:

•Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing excavation along the western section to ... (Full Story & Photos)

Divider
Construction Update 12.3.24

Secretary CHRISTINE DENNETT, December 03

New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring to Begin

Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project is moving forward with significant developments.

Key Updates Include:


•Excavation Work: Excavation has begun along the southwest and western portions of the site, clearing the area for the upcoming footings and ... (Full Story & Photos)

No Caption
Divider
Construction Update 11.27.24

Secretary CHRISTINE DENNETT, November 27

News Update: New Castle Fire District No.1 Modernization Project Update: Excavation and Footing Work to Begin

Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project is moving forward with exciting developments. The project team is set to begin excavation work and the forming of footings along the southwest portion of the site. Additionally, excavation of soil along the western portion ... (Full Story)


Divider

Your feedback is important to us!  Feel free to sign the guestbook.


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)