New Castle Fire District No.1

 
 

Upcoming Events

11/17/2025
Project Meeting with Contractors (weekly)

11/19/2025
Board of Commissioners Regular Meeting

11/24/2025
Project Meeting with Contractors (weekly)

12/01/2025
Project Meeting with Contractors (weekly)

12/08/2025
Project Meeting with Contractors (weekly)

12/08/2025
Board of Commissioners Project Special Meeting

12/09/2025
Annual Fire District Election

12/15/2025
Project Meeting with Contractors (weekly)

12/17/2025
Board of Commissioners Regular Meeting

12/22/2025
Project Meeting with Contractors (weekly)

12/29/2025
Project Meeting with Contractors (weekly)

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
377,793
Visitors Today
Nov 11, 2025
165

Welcome to New Castle Fire District No.1


he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.

Divider
Construction Update 11.9.25

Secretary CHRISTINE DENNETT, November 09

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates – November 9, 2025

Overall Progress
Phase One of the modernization project remains on schedule for substantial completion by March 2026. Crews are taking advantage of the mild fall weather to continue exterior and interior work before winter conditions arrive.

Exterior Work
Brick and precast installation continues ... (Full Story & Photos)

Decorative Stonework Installation
Decorative Stonework Installation

Divider
No Caption Construction Update 10.27.25

Secretary CHRISTINE DENNETT, October 27

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates – October 27, 2025

Construction Progress

Phase One of the project remains on track for substantial completion by March 2026. Coordination between trades continues to ensure all systems and pours are scheduled efficiently ahead of colder weather.

Plumbing & Mechanical

The backflow preventers for the project have ... (Full Story & Photos)

Divider
Construction Update 10.13.25

Secretary CHRISTINE DENNETT, October 13

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates – October 13, 2025

Construction Progress
Phase One of the project remains on track for substantial completion by March 2026.

Roof Work
Shingle installation is complete. All lower roofs now have roofing material installed. Work on the upper roof, adjacent to the existing firehouse, will continue this week. Roof ... (Full Story & Photos)

Apparatus Bays
Apparatus Bays

Divider
Construction Update 10.6.25 Sewer Lining Project

Secretary CHRISTINE DENNETT, October 06

As part of ongoing maintenance efforts, a sewer lining project is scheduled to take place on Wednesday, October 8th. The work is expected to be completed in one day.

Key Details:
• Date of Work: Wednesday, October 8th
• Duration: One day (weather permitting)
• Traffic Impacts: There may be temporary traffic disruptions in the area while work is underway.

We are working diligently to minimize any ... (Full Story)


Divider
Construction Update 9.30.25

Secretary CHRISTINE DENNETT, September 30

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates – September 30, 2025

Construction Progress
Phase One of the project remains on track for substantial completion by March 2026.

Roof Work
The roofing crew has mobilized on-site and is progressing quickly. All shingle underlayment has been installed over the main roof truss system. Shingle installation is underway, ... (Full Story & Photos)

No Caption
Divider
No Caption Construction Update 9.15.25

Secretary CHRISTINE DENNETT, September 15

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Construction Progress
• Phase One substantial completion remains targeted for March 2026.
• All roof trusses have been successfully installed, and the crane has demobilized ahead of schedule—a significant milestone in the structural work.
• Carpenters are now shifting focus to installing roof sheathing and framing ... (Full Story & Photos)

Divider
Construction Update 8.25.25

Secretary CHRISTINE DENNETT, August 25

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Construction Progress
• Phase One substantial completion March 2026.
• Structural steel framing and metal decking work are ongoing.
• Preparations continue for the second-floor deck concrete pour and additional at-grade concrete work.
• Installation of the steel landing deck in the S04 stair enclosure is also underway.

Interior ... (Full Story & Photos)

West Side
West Side

Divider
Construction Update 8.13.25

Secretary CHRISTINE DENNETT, August 13

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Sewer Permit Approved

The Town of New Castle has approved the sewer permit for both the sewer repair points and connection work. The signed permit has been received, and scheduling is underway for the site contractor to mobilize and perform the necessary work.

Updated Schedule

Phase 1 of the firehouse is now ... (Full Story)


Divider

Your feedback is important to us!  Feel free to sign the guestbook.


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)