Welcome to New Castle Fire District No.1
he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.
|
Construction Update 1.22.25
Secretary CHRISTINE DENNETT, January 22
New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, Concrete Pouring Underway Chappaqua, NY
The New Castle Fire District No. 1 Modernization Project continues to make substantial progress, with essential construction activities advancing as planned.
Key Updates Include:
•Excavation Work: Excavation has been completed along the southwest section of the site, and work ... (Full Story)
|
Construction Update 1.15.25
Secretary CHRISTINE DENNETT, January 15
New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, Concrete Pouring Underway
Chappaqua, NY
The New Castle Fire District No. 1 Modernization Project continues to make substantial progress, with essential construction activities advancing as planned.
Key Updates Include:
•Excavation Work: Excavation has been completed along the southwest section of the site, and work ... (Full Story)
|
Construction Update 1.8.25
Secretary CHRISTINE DENNETT, January 08
New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway Chappaqua, NY
The New Castle Fire District No. 1 Modernization Project continues to make significant strides, with key construction activities progressing on schedule.
Key Updates Include:
•Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing ... (Full Story)
|
Construction Update 12.31.24
Secretary CHRISTINE DENNETT, December 31
New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway Chappaqua, NY
The New Castle Fire District No. 1 Modernization Project continues to make significant strides with key construction activities progressing on schedule.
Key Updates Include:
•Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing ... (Full Story)
|
Construction Update 12.19.24
Secretary CHRISTINE DENNETT, December 19
New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway Chappaqua, NY
The New Castle Fire District No. 1 Modernization Project continues to make significant strides with key construction activities progressing on schedule.
Key Updates Include: •Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing ... (Full Story & Photos)
|
|
|
Construction Update 12.10.24
Secretary CHRISTINE DENNETT, December 10
New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway Chappaqua, NY
The New Castle Fire District No. 1 Modernization Project is progressing with key activities moving forward.
Key Updates Include:
•Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing excavation along the western section to ... (Full Story & Photos)
|
Construction Update 12.3.24
Secretary CHRISTINE DENNETT, December 03
New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring to Begin
Chappaqua, NY
The New Castle Fire District No. 1 Modernization Project is moving forward with significant developments.
Key Updates Include:
•Excavation Work: Excavation has begun along the southwest and western portions of the site, clearing the area for the upcoming footings and ... (Full Story & Photos)
|
|
Construction Update 11.27.24
Secretary CHRISTINE DENNETT, November 27
News Update: New Castle Fire District No.1 Modernization Project Update: Excavation and Footing Work to Begin
Chappaqua, NY
The New Castle Fire District No. 1 Modernization Project is moving forward with exciting developments. The project team is set to begin excavation work and the forming of footings along the southwest portion of the site. Additionally, excavation of soil along the western portion ... (Full Story)
|
Your feedback is important to us! Feel free to sign the guestbook.
|